That Report CRS-2024-22 Amendment to the Community & Recreation Services 2024 One (1) Year Capital Works Plan – Arena Restoration, be received;
And that the proposed work of the Arena’s exterior building envelope as described in Report CRS-2024-22 be added to the Community and Recreation Services 2024 One (1) Year Capital Works Plan, Arena Restoration Project;
And further that the Arena Restoration Project budget be increased by up to $338,000 (before HST) and be funded from the Infrastructure Reserve as outlined in Report CRS-2024-22;
And furthermore, that the awarding for the interior and exterior work as described in Report CRS-2024-22, be authorized to proceed as a single source negotiation;
And furthermore, that an upset limit of $138,000 for completion of the interior work and an upset limit of $200,000 for completion of the exterior work be added to the original tender award of $2,541,618 (before HST) to TCI Titan Contracting Inc for a revised award total of $2,879,618.